* You have prepared the following schedule for a project in

Reading Time: < 1 minute

* You have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project. Activities Aand D require one tractor to complete while activities B, C, E and F require2 tractors.Develop a resource-constrained schedule in the loading chart that follows.Use the parallel method and heuristics given. Be sure to update each period asthe computer would do. Record the early start (ES), late finish (LF) and slack(SL) for the new schedule